Plan for Success

20 Step Process For A Successful Large Tree Transplanting

  1. Use Template to layout dig area, and then dig sides.
  2. Assemble The Box with cutting blade and lift assembly.
  3. Dig holes for box, cables and hydraulic pulling system.
  4. Position box and pulling system in holes.
  5. Connect cables, hydraulics then pull box under tree.
  6. Remove cutting blade, then add and bolt the four sides.
  7. Mud-in voids between the box sides and tree roots with water, soil and soil additives.
  8. Bolt on lifting assembly.
  9. Lift, lay-down and tie tree for transporting.
  10. Load tree for transporting.
  11. Secure and tarp tree for transport.
  12. On arrival remove tarp and untie tree.
  13. Unload tree to staging area.
  14. Right the tree and re-cable for lifting.
  15. Crane tree into place in the planting pit.
  16. Remove bolts attaching sides to bottom.
  17. Pull the two bottom plates individually with hydraulics.
  18. Unbolt and remove lift assembly and sides from the planting pit.
  19. Backfill planting pit with approved soil mix and water to fill voids and eliminate air pockets.
  20. Smooth, fill and grade to finish elevation.

Note:

  • These steps are for transporting large tree on highway, if tree is moved to another location, on site, steps 9 – 14 would change depending on distance to be moved.
  • If tree is to be stored, steps 9 – 14 would change and the metal sides would be replaced with a Temporary Storage Box constructed of root pruning fabric with a wooden frame connected to the ship plates. At replanting time fabric and wood frame would be removed and metal sides with lift assembly will be re-attached for lifting and transporting.

Our Projects

At Urban Forestry Works, we have the privilege of enhancing landscapes nationwide. From saving large historic oaks, to providing new mature landscape for upscale developments, golf courses, and municipalities, our family continues to take pride in our mission of honoring every tree’s story.

Eastern Wharf

Eastern Wharf

Urban Forestry Works supplied and installed 12″-24″ caliper specimen live oaks for the 54 acre Eastern Wharf project. This mixed-use project along the Savannah River in Savannah, GA hosts residences, office space, parks, a hotel, restaurants, and bars. These trees...

Beacon Lakes

Beacon Lakes

UFW supplied and installed 14" Caliper Live Oaks to the main entrance and roadway of Beacon Lakes Development in St. Johns, FL. The trees were focal points for the development's entrance to help establish curb appeal and beautify the landscape with large canopy live...

Jesuit High School of Tampa

Jesuit High School of Tampa

In getting ready for the new school year, UFW was contacted by Jesuit High School to add some life to the Student Commons area on campus. Being that this area brings a lot of traffic by students throughout the day, it was important that UFW bring in a tree that had a...